Principal Designer not releasing the pre construction info

Post by Safety4PMplonker »

Hello all,

We're a contractor under CDM but 90% of the work in the CDM will be managed by us. There is an appointed PD, and the PC is still to be appointed.

We have been asking the PD when the pre construction info will be available and they have said they will not issue this to us, but will to the PC once appointed they will issue it to us.

My understaind is that the PCI info needs to be made available to all contractors and designers as soon as is available, which is my experience but also my intepreation of CDM. So the PD not issuing it is them being awkward for some reason

Can I have comment on who is correct here?

Thanks
User avatar
WillPool
HSfB Moderator
HSfB Moderator
Posts: 11372
Joined: Mon Mar 13, 2006 8:45 pm
18
Industry Sector: Construction/Civils/Telecomms
Occupation: Regional Safety Director
Location: Tabuk - Saudi Arabia
Has thanked: 39 times
Been thanked: 715 times
Contact:

Re: Principal Designer not releasing the pre construction info

Post by WillPool »

You say you are a contractor under CDM?

Are you the principal contractor (PC)?

For me this is about contracts not CDM, the PD will issue to the PC, and its up to them to disseminate the information to any other contractors.

Until the Client appoints a PC then the PD assumes responsibility until the PC is appointed.

Thats my take on what you have said within the post.

Will .salut
It is better to be careful 100 times than to get killed once.
Mark Twain (1835 - 1910)
Safety4PMplonker
Newbie
Newbie
Posts: 5
Joined: Thu Nov 14, 2024 9:50 am
Has thanked: 1 time

Re: Principal Designer not releasing the pre construction info

Post by Safety4PMplonker »

Thanks for replying

No we are not the PC, they are still to be appointed.

Ok to be clear your view is there is nothing under CDM that states they shouldn't/can't share the PCI info with us?
User avatar
WillPool
HSfB Moderator
HSfB Moderator
Posts: 11372
Joined: Mon Mar 13, 2006 8:45 pm
18
Industry Sector: Construction/Civils/Telecomms
Occupation: Regional Safety Director
Location: Tabuk - Saudi Arabia
Has thanked: 39 times
Been thanked: 715 times
Contact:

Re: Principal Designer not releasing the pre construction info

Post by WillPool »

They could share the PCI with you but usually they will issue to the info to the PC first so any site conditions can be evaluated etc by the PC and they can introduce correct mitigation/site rules into place, before any contractor gets on site or makes their own rules up, contractors may have a good setup but setting out or setting site rules without the PC can be a bit of a no-no.

As I say, probably more to do with contracts and insurance than direct CDM regs

Will .salut
It is better to be careful 100 times than to get killed once.
Mark Twain (1835 - 1910)
Post Reply

 

Access Croner-i Navigate Safety-Lite here for free

HSfB Facebook Group Follow us on Twitter Find us on Facebook Find us on on LinkedIn

Terms of Use Privacy Policy