Page 1 of 1

Question for CDM experts please

Posted: Thu Sep 24, 2020 6:04 pm
by Ewangoil
As a result of a recent fire risk assessment we carried out our client is needing to get some remedial work done on their building. The work will involve joiners, plumbers and electricians although each job relates to separate actions.
The work won't be notifiable as it won't meet the criteria for that.
My question is, will the client be required to appoint a principal designer and principal contractor as none of the work is directly related to each other? e.g. Can it be viewed as 3 separate projects and therefore each project will only involve a single contractor?

I hope that makes sense and someone can enlighten me

Thanks

Re: Question for CDM experts please

Posted: Fri Sep 25, 2020 12:06 pm
by Alexis
bump

Re: Question for CDM experts please

Posted: Fri Sep 25, 2020 12:28 pm
by Ewangoil
Thanks Alexis

Re: Question for CDM experts please

Posted: Fri Sep 25, 2020 1:34 pm
by Alexis
No problem Ewan. I am sure someone will reply when they have a moment.