CDM 2015 - can you be principle designer and principle contractor?

Post by TWDB »

All,

Quick question I hope, can anyone advise?

Under 2015-

can a company be a principle design and principle contactor.

and can the PD responsibilities be changed during a project from PD to the PC?

Thanks

T
Update: taken a new job :D hopefully confidence and positivity will return with new challenge - scary though leaving current place after 16 years (6 years H&S !) :shock:
(previous signature: was motivated once ..................... searching to get it back ! .scratch)
User avatar
WillPool
HSfB Moderator
HSfB Moderator
Posts: 10779
Joined: Mon Mar 13, 2006 8:45 pm
18
Industry Sector: Construction/Civils/Telecomms
Occupation: Regional Safety Director
Location: Tabuk - Saudi Arabia
Has thanked: 24 times
Been thanked: 311 times
Contact:

Re: CDM 2015 - can you be principle designer and principle contractor?

Post by WillPool »

The requirement under the regs is if there is more than one contractor, a separate dutyholder should be appointed to co-ordinate the design and construction phases of a project. The Regs do not say who that should be, only that the appointment must be in writing, and should have the necessary skills experience, competency and training (or words to that effect) to carry out the appointment.

So a design and build contractor could be appointed as both PD & PC. Be careful though you can only have one Principle Designer or COntractor on each project, someone must take overall responsibility for all other designers and contractors.

The appointment could change during a project and this would need to be documented and a thorough handover. The PD can also handover the role to the PC if their appointment ends before the construction phase has ended, The regulations have a set of criteria that has to be met, i.e what risks are designed in/out amongst others.

A link to the regs is below:

http://www.hse.gov.uk/pUbns/priced/l153.pdf

Hope this helps

Will .salut
It is better to be careful 100 times than to get killed once.
Mark Twain (1835 - 1910)
User avatar
TWDB
Snr Member
Snr Member
Posts: 390
Joined: Thu Apr 11, 2013 3:24 pm
11
Industry Sector: Civil Eng, HV Elec, Remediation Soil/Wat
Occupation: SHEQ Manager
Location: UK WIDE
Has thanked: 177 times
Been thanked: 29 times

Re: CDM 2015 - can you be principle designer and principle contractor?

Post by TWDB »

Thanks Will great stuff
T
Update: taken a new job :D hopefully confidence and positivity will return with new challenge - scary though leaving current place after 16 years (6 years H&S !) :shock:
(previous signature: was motivated once ..................... searching to get it back ! .scratch)