Hi all,
Is a CPP required for removal of large equipment from a business?
Many thanks.
Constuction Phase Plan
Moderator: Moderators
-
- Jnr Member
- Posts: 182
- Joined: Thu Jan 01, 2015 9:18 pm
- 9
- Industry Sector: Health and Safety Consultant
- Occupation: DSEAR Risk Assessor
- Location: Uffculme, Devon
- Has thanked: 30 times
- Been thanked: 40 times
- Contact:
- bernicarey
- Anorak Extraordinaire
- Posts: 8973
- Joined: Tue Jan 13, 2009 2:50 am
- 15
- Twitter: @bernicarey
- Industry Sector: Consultancy/Training
- Occupation: Safety, Health, Environment and Fire Consultant.
- Location: The heart of the East Midlands...
- Has thanked: 76 times
- Been thanked: 300 times
- Contact:
Re: Constuction Phase Plan
Probably, depends on what you're talking about.
Is the work within the definition of 'Construction' because the answer will help...
Have you tried looking at the HSE website for the list of the sort of stuff that is covered?
Go and read up on L153, that should help.
doesn't really give much detail.removal of large equipment from a business
Is the work within the definition of 'Construction' because the answer will help...
Have you tried looking at the HSE website for the list of the sort of stuff that is covered?
Go and read up on L153, that should help.
-
- Jnr Member
- Posts: 182
- Joined: Thu Jan 01, 2015 9:18 pm
- 9
- Industry Sector: Health and Safety Consultant
- Occupation: DSEAR Risk Assessor
- Location: Uffculme, Devon
- Has thanked: 30 times
- Been thanked: 40 times
- Contact:
Re: Constuction Phase Plan
Thanks for the direction Bernie.
The company has sold a large piece of machinery which will be dismantled and removed from one of our work units. I have had a google and found that removal for decommissioning / refurbishment will require CDM 2015 regulations.
I'm not Construction qualified but am reading through L153 at the moment. The contractor we are using have their own H&S person so I will liaise with her over our duties.
Many thanks,
Stretch
The company has sold a large piece of machinery which will be dismantled and removed from one of our work units. I have had a google and found that removal for decommissioning / refurbishment will require CDM 2015 regulations.
I'm not Construction qualified but am reading through L153 at the moment. The contractor we are using have their own H&S person so I will liaise with her over our duties.
Many thanks,
Stretch
- bernicarey
- Anorak Extraordinaire
- Posts: 8973
- Joined: Tue Jan 13, 2009 2:50 am
- 15
- Twitter: @bernicarey
- Industry Sector: Consultancy/Training
- Occupation: Safety, Health, Environment and Fire Consultant.
- Location: The heart of the East Midlands...
- Has thanked: 76 times
- Been thanked: 300 times
- Contact:
Re: Constuction Phase Plan
It's the definitions in Reg 2 that you need to get your head around.
There's quite a lot there....
There's quite a lot there....